Clause 14 of the 1999 FIDIC Silver Book contains the provisions regarding advance payment, the interim and final payment requirements, as well as the procedures for the submission of the various statements that are used to apply for these payments.
In this document, you will find the key issues and the procedure regarding the payments under the 1999 FIDIC Silver Book.
The Employer shall pay the first instalment after receiving;
1. A Statement (under Sub- Clause 14.3 [Application for Interim Payments])
2. The Performance Security in accordance with Sub-Clause 4.2 [Performance Security]
3. A guarantee in amounts and currencies equal to the Advance Payment
Except as otherwise stated in Sub-Clause 2.5 [Employer’s Claims], the Employer is to pay the first instalment;
➤ Within 42 days after the Contract came into full force and effect
or
➤ Within 21 days after the Employer’s receiving the relevant documents in accordance with Sub-Clause 4.2 [Performance Security] and Sub-Clause 14.2 [Advance Payment]
whichever is later.
1. The Contractor submits six copies of the statement to the Employer after the end of the period of payment stated in the Contract (if not stated, after the end of each month).
2. The Employer approves the form of the Statement.
3. The amounts are to be demonstrated in detail.
4. Progress report in accordance with Sub-Clause 4.21 [Progress Reports] and other supporting documents are to be included.
The Statement should include;
➤ The estimated contract value of the Works executed and the Contractor’s Documents produced till the end of the month. Variations should be included.
The below mentioned items should be excluded;
➤ Any amounts to be added and deducted for;
➤ The deduction of amounts;
Within 28 days after receiving the Statement and the supporting documents, the Employer is to give Notice of any items with which he disagrees.
Except as otherwise stated in Sub-Clause 2.5 [Employer’s Claims], the Employer is to pay the amount that is due in accordance with each statement:
➤ Within 56 days after receiving the Statement and supporting documents
1. The Contractor is to pay the whole of the balance outstanding, if the Advance Payment has not been repaid prior to the issuance of the Taking-Over Certificate.
2. After the issuance of the Taking-Over Certificate and Works have passed the specified tests, the first half of the Retention Money is to be paid to the Contractor.
Within 84 days after receiving the Taking-Over Certificate for the Works, the Contractor shall submit to the Employer six copies of a Statement at completion with supporting documents, in accordance with Sub-Clause 14.3 [Application for Interim Payments], showing [1] ;
(a) The value of all work done in accordance with the Contract up to the date stated in the Taking-Over Certificate for the Wo ks
(b) Any further sums which the Contractor considers to be due
(c) An estimate of any other amounts which the Contractor considers will become due to him under the Contract
The Employer is to give Notice of any items with which he disagrees within 28 days after receiving the Statement and supporting documents.
Except as otherwise stated in Sub-Clause 2.5 [Employer’s Claims], the Employer is to pay the amount that is due in accordance with “Statement at Completion”.
➤ Within 56 days of receiving the Statement and supporting documents.
1. Promptly after the latest of the expiry dates of the Defects Notification Periods, the outstanding balance of the Retention Money shall be paid to the Contractor.
2. However, if any work remains to be executed under Clause 11 [Defects Liability] or Clause 12 [Tests after Completion], the Employer shall be entitled to withhold the estimated cost of this work until it has been executed.
The Performance Certificate is to be deemed to constitute the acceptance of the Works. The Employer is to issue the Performance Certificate within 28 days after the latest of the [3] ;
➤ Expiry dates of the Defects Notification Period
➤ As soon thereafter as the Contractor has;
Within 56 days after receiving the Performance Certificate, the Contractor shall submit, to the Employer, six copies of a draft final statement including:
➤ The value of all work done
➤ Any further sums which the Contractor considers to be due to him
In the event of the Employer’s disagreement the Contractor is to submit further information and make changes.
After these, the Contractor is to submit the Final Statement as agreed.
Except as otherwise stated in Sub-Clause 2.5 [Employer’s Claims], the Employer is to pay the final amount due in accordance with Sub-Clause 14.11 [Application for Final Payment] and Sub-Clause 14.12 Discharge].
➤ Within 42 days after receiving the Final Statement and written discharge.
FOOTNOTES
1. The same Sub-Paragraph letters are used as in Sub-Clause 14.10 [Statement at Completion] of the 1999 FIDIC Silver Book.
2. The same Sub-Paragraph letters are used as in Sub-Clause 14.9 [Payment of Retention Money] of the 1999 FIDIC Silver Book.
3. The same Sub-Paragraph letters are used as in Sub-Clause 11.9 [Performance Certificate] of the 1999 FIDIC Silver Book.
This information is provided for your convenience and does not constitute any “Legal Advice”. This document is prepared for the general information of the interested persons. This should not be acted upon in any specific situation without appropriate legal advice.
This information may not be reproduced or translated without the prior written permission of eayglobal.com
For further information please contact eay@eayglobal.com